11 ONE SHOT INSTALLATION PROCEDURE
This section of the manual describes the basic connection procedure.
The truck needs (to move) a minimum I/O dotation that it is mandatory: this
minimum dotation is listed in the Steps from 1 to 8 below.
Step1 Connect a potentiometer in the range 0.5K to 10Kohms, to modify
the wished speed, between CNB#12, CNB#10, CNB#11.
Step2 Connect two travel demand switches. The FWD travel demand must
be connected between a battery (key) voltage and CNB#6. The
REV travel demand must be connected between a battery (key)
voltage and CNB#5. Only one of them can be active at the same
time. They become active when connected to a key voltage (the key
voltage is supplied on the CNB#2 connection).
Step3 Connect a tiller (or seat) switch enabling/disabling the truck motion
between CNB#3 and a key voltage. It becomes active, enabling the
motion, when closed to a key voltage (the key voltage is supplied on
the CNB#2 connection).
Step4 Connect the encoder in the motor shaft between CNA#9=VDD,
CNA#10=GND, CNA#19=CHA, CNA#20=CHB. The VDD voltage
may be 13V or 5V depending on a jumper inside the controller (see
also 8.4).
Step5 Connect the plus battery voltage through a key switch at the KEY
input CNB#1 (this is the input for the logic supply).
Step6 Connect the Main Contactor Coil to CNA#1 and CNA#2. The
contactor must make and take the plus battery power cable to the
+BATT power terminal of the AC1.
Step7 Connect the motor and the minus battery to the corresponding
power terminals of the AC1.
Step8 Connect the Electromechanical Brake between CNA#3 and the tiller
switch (when the tiller switch opens, the electromechanical brake
gets de-energized braking the truck). A 3Ampere freeweeling diode
(arc soppressor) with the anode to CNB#3 must be connected in
parallel with the Electromechanical Brake Coil.
The Steps from 1 to 8 describe the installation operations that is mandatory to do
in order your truck moves. Obviously the AC1 may execute a wider set of optional
services as:
1) to handle some speed reductions requests
2) to handle a analog sensor inside the motor
3) to handle a proportional braking
4) to handle an On/Off forks lowering valve
5) to handle a pump contactor
6) to handle a belly switch and an Inching operative mode
7) to handle the communication via CAN Bus with our MDI-PRC
8) to handle a proportional input for the forks lifting/lowering
You must fill your I/O dotation with your optional functions. The optional functions
are shown in the connecting drawing and descripted in detail inside this manual.
The index may help you.
Vue de la page 26
1 2 ... 22 23 24 25 26 27 28 29 30 31 32 ... 72 73

Commentaires sur ces manuels

Pas de commentaire